Construction at the Beaverton Public Safety Center is really picking up momentum. The drier than usual weather has allowed work to progress nicely without turning the site into a muddy mess.

Sub-contractors are starting to dig footings in preparation of foundation work and many site development activities are taking place including storm water trenching and installation of water lines on the site.

The concrete and electrical sub-contractors are now on site and have begun preliminary work on the foundation and electrical conduit throughout the project site.

The building footings are currently being dug out and the concrete workers are making forms and will start hauling concrete in the next couple of weeks. Many construction supplies are being staged for the next phase, foundation work.